Arcs in a project network indicate
a. completion times.
b. precedence relationships.
c. activities.
d. None of the alternatives above is correct.2. Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 12, 15, and 10, then the earliest start time for W
a. is 10.
b. is 12.
c. is 15.
d. cannot be determined.3. When activity times are uncertain,
a. assume they are normally distributed.
b. calculate the expected time, using (a 4m b)/...